This is a whole-home renovation project on a 1930s home in Auburn, Maine. This home will be fully gutted and renovated, bringing it back to life and modernizing it on the interior. Check back often to see updates!
Colonial Revival Project – Project Updates
Wed, May 6
Cabinets delivered today! Interior trim continues – second floor doors and windows are complete. First floor in progress Many items delivered by Emily today – light fixtures, mirrors, ceiling fan, etc
Fri, May 1
Basement shelving completed Initial priming/paint completed Vanities received and in house to be installed next week Interior door and trim installation in progress. two doors will be swapped out due to mfg error. Electrician has started installing some outlets and switches Cabinets expected in next Wednesday 5/6
Fri, Apr 17, 2026
Drywall complete! Electrical panel swap completed this week Painters scheduled for Tuesday Interior doors to be delivered next Friday
Mon, Apr 6, 2026
Powder Room Vanity was delivered today with significant damage. Reported issue to Nineteen Skies to file a claim on it. Drywall crew was on site today finishing up stairway and cleaning up. Trevor was on site this afternoon installing the shower Drywall crew was back to finish remaining drywall in bath and kitchen ceiling
Fri, Apr 3, 2026
Drywall Hanging nearly completed. Shower kit delivered this week – floor plan was found to have a crack and a replacement was delivered Thursday. Plumber will be on site Monday to install. Drywall crew will return after to finish the few spaces left open for shower install. Glass Shower Door kit delivered and inspected – all is good. Mudding/Taping to begin next Tuesday/Wednesday.
Thu, Mar 26, 2026
Insulation crew finished up the batt insulation this morning. Insulation inspection was completed today at 11am and passed. We will clean up and prep for drywall next week. Drywall delivery has been delayed until potentially Tuesday – they are a bit behind schedule due to posted roads and other jobs running long.
Wed, Mar 25, 2026
Insulation videos from this morning. New exterior door installed with temporary hardware.
Wed, Mar 18, 2026
Building inspection passed ✅
Electrical inspection passed ✅
Plumbing inspection pending approval
Ductwork modifications completed this week.
Basement daylight walls opened up – insulation scope expanded to include those.
Elevations provided by Brady-Anne were verified in the field today with no issues to report Insulation will begin tomorrow.
Expected to take 4-5 days. Insulation inspection scheduled for next Thursday. Drywall materials will be delivered Friday.
Mon, Mar 9, 2026
“Window installation has begun. Venting for hood and bathrooms installed. Basement staircase has been replaced. Plumbing rough in completed. Electrical rough in will start tomorrow.”
Fri, Feb 27, 2026
“Framing nearly complete. A few small pieces to finish next week. Cast iron pipe removed and replaced with pvc Living room converted to cathedral ceiling Flooring selections finalized Windows will be delivered Tuesday and installed next week. Plumber will be back on site early next week Electrician on site late next week”
“Demo nearing completion with roughly a few days remaining. Reports of potential trouble in the neighborhood last night. Stopped by house today to confirm all was secure. Double checked windows and doors. Everything is in good shape.”
Fri, Jan 23, 2026
“Demolition continues – lots of progress made! Should wrap up with demo next week and we’ll start assessing framing repairs and modifications for the new layout.”
1/20/26
Demo has officially begun!
Permits obtained from city of Auburn
Water has been shut off
Some electrical has been disconnected
Dumpster on site with protection for driveway